Stone Fabrication Facility Construction – Wilmington, Massachusetts
A 44,400 SF industrial fabrication and showroom facility constructed for Gerrity Stone
Overview
This 44,400 SF stone fabrication facility was designed, permitted, and constructed to support large-scale production, material handling, and showroom operations for Gerrity Stone in Wilmington, Massachusetts. The project was delivered through the integrated design-build approach of McCarty Companies, with civil engineering and permitting services provided by McCarty Engineering and construction completed by McCarty Associates.
The site was formerly home to a chemical coating factory, with two existing buildings totaling 26,800 SF requiring full abatement and demolition to make way for the new construction. Site design presented unique challenges, as 12 additional existing buildings were required to remain in service throughout all phases of construction. Environmental conditions further influenced the project scope, with wetlands and a shallow groundwater table necessitating a highly engineered stormwater management approach incorporating a Constructed Stormwater Wetland designed by McCarty Engineering.
The new building is a 44,400 SF pre-engineered metal structure with insulated metal panel siding. The front portion of the facility was designed as a clear-span space to support two 10-ton overhead cranes with 72-foot spans, while the rear production area houses four 2-ton bridge cranes, two jib cranes, and a dedicated water recycling system. Office and showroom spaces are integrated into the front of the building. Construction began in April 2021 and was completed in May 2022 by McCarty Associates, under the integrated project delivery structure of McCarty Companies.

Key features

Building design
- • 44,400 SF pre-engineered metal building
- • Insulated metal panel exterior siding
- • Clear-span front production area
- • Integrated office and showroom spaces
Production and material handling
- • Two (2) 10-ton overhead cranes with 72-foot spans
- • Four (4) 2-ton bridge cranes
- • Two (2) jib cranes
- • Dedicated water recycling system
Site and environmental
- • Redevelopment of former chemical coating facility
- • Abatement and demolition of two buildings (26,800 SF)
- • 12 existing buildings remained operational during construction
- • Constructed Stormwater Wetland for runoff mitigation
- • Design accommodating shallow groundwater and wetlands
Permitting and schedule
- • Site Plan Approval from Town of Wilmington Planning Board
- • Order of Conditions from Conservation Commission
- • Construction start: April 2021
- • Construction completion: May 2022